Construction Packet

Save this link as a bookmark for current or future builds for easy reference. 

Pre Development link within page exceptions

These times do not include weekend or holidays. This plan review time-table applies across the board. Development Services (DS) determines the dates in the date range established as follows:
1st Review2nd Review3rd Review and any Additional Reviews
Site Plan
7-10 days3-5 days2-3 days
Site Development Permit7-30 days7-15 days5-15 days
Plat7-10 days3-5 days2-3 days
Zoning7-10 days3-5 days2-3 days
Minor Plat3-5 days3-5 days2-3 days
Residential Permit2-3 days2-3 days2-3 days
Commercial Permit (new or remodel)7-10 days5-7 days2-3 days
Commercial Single Trade (solar, elec., plumb., mech., retaining wall., ect. )3-5 days2-3 days2-3 days
Certificate of Occupancy3-5 days2-3 daysCommercial Remodel
Pre Development Meeting Request 2-3 days2-5 days2-3 days
All other permits not listed2-7 days